AL-Murry – Alyn Road Project Yankul

AL-Murry – Alyn Road Project Yankul

Our Scope Of Work

Complete Structure work of bridge & culverts

Culverts:

35 km Length

Total no of box culverts are 39

Detail of box Culverts:

39 cell size(4×2), 22 cell (4×2), 19 cell (4×2), 15 cell (4×2), 5 cell (4×2).

Total no of I-GIRDERS are 48 (28 meter Length 1.7 meter height)

Project Details

Main Contractor:

Khalid Bin Ahmed & Sons L.L.C

Client:

Ministry of Transport & Communication

Consultant:

Al-Manarah Engineering Consultancy

Duration/Year Completed:

2014